🏠 Home How to use e-mentor 🎁 Earn Gifts by Studying
📚 Study Hub
🤖 AI Study PlannerPAID 🔁 Recap Cards ⚔️ 1v1 Study Duels NEW 📋 Test Series 💎 Test Series PackagesTIERS 🎁 Invite FriendsFREE PLANNER 📖 Track Chapters
⚡ Focus & Tools
🎧 Virtual Focus Room LIVE ⏱ Pomodoro Timer 🏆 Leaderboard 🎁 Earn Gifts by Studying
🌐 Community & Info
✍️ Blog ❓ Frequently Asked Questions ℹ️ Read Me First
Login Join Free
📢 UPDATES
📅 25th All India Debate Competition 2026  |  🏆 Leaderboard resets weekly — Keep your streak alive!  |  💡 Join Discussion Board for exam doubt clearing  |  📅 25th All India Debate Competition 2026  |  🏆 Leaderboard resets weekly — Keep your streak alive!  |  💡 Join Discussion Board for exam doubt clearing  | 

Ch 11: NETWORK ANALYSIS – PERT, CPM — Previous Year Exam Questions (PYQ)

Final 📚 Strategic Cost Management 📖 Ch.11 — NETWORK ANALYSIS – PERT, CPM ⭐ V1: Previous Year Question (PYQ) ⚡ Free Mode (Answers Locked)
⏱ Duration: 54 Mins 🎯 Total Marks: 30 Passed at: 12 Marks Max Attempts: 10
⚖️ Statutory Applicability: AY 2026-27 & Current Institute Curriculum

Answer ALL questions. Working notes / statutory sections must form part of the answers.

Login to Enroll & Start Join Free

📑 Exam Questions

6 Questions • Total 30 Marks

1(a): Time Estimates and Critical Path in Network Analysis

5 Marks
The network is drawn as follows : Network Diagram Various paths Duration of paths (days) (i) 1-2-4-6-7 10 + 5 + 6 + 7 = 28 (ii) 1-2-3-4-6-7 10 + 4 + 0 + 6 + 7 = 27 (iii) 1-2-3-5-6-7 10 + 4 + 0+4 + 7 = 25 (iv) 1-2-5-6-7 10 + 7 + 4 + 7 = 28 Critical paths are 1-2-4-6-7 and 1-2-5-6-7 with duration of 28 days and are marked with double lines. (b) Raw Materials P Q R Available Units A - B C - Profits 3/- , 5/-, 4/- Let x1 be the number of units of P Let x 2 be the number of units of Q Let x 3 be the number of units of R (i) Formulation of the problem Objective function: Max Z = 3x1 + 5x2 + 4x3 Subject to constraints: 2x1+3x3 ≤8 3x1+2x2+2x3 ≤10 5x2+4x3 ≤15 X1, X2, X3 ≥0. (ii) Dual of the problem Min C = 8y1+10y2+15y3 Subject to constraints: 2y1+3 y 2 ≥3 2 y 2+5 y 3 ≥5 3 y 1+2 y 2+4 y 3 ≥4 y 1, y 2, y 3 ≥ 0. SUGGESTED_ANSWERS TO QUESTIONS_SYL2016_DEC2017_PAPER-15 Academics Department, The Institute of Cost Accountants of India (Statutory Body under an Act of Parliament) Page 17 8. Write short notes on any four of the following: (a) Usefulness of Pareto Analysis (b) Seven Principles of BRR (c) Four P’s of TQM (d) Lean Accounting (e) Value Engineering Answer:
🔒 Official Model Solution
Model answers and self-evaluation solutions are available in the Premium Tier & Rankers Plan.
Unlock Answers (₹1,000)

1(b): Time Estimates and Critical Path in Network Analysis

5 Marks
Critical Path = H G B   Expected Duration = 48 Days. Standard deviation of overall duration = 3.27 days
🔒 Official Model Solution
Model answers and self-evaluation solutions are available in the Premium Tier & Rankers Plan.
Unlock Answers (₹1,000)

2(a): Time Estimates and Critical Path in Network Analysis

5 Marks
Probability of finishing the Project in 54 days = 96.67 % (iv) Probability of finishing the Project in 54 days = 92.222 % This has fallen due to increase variability of the activities on the Critical path.
🔒 Official Model Solution
Model answers and self-evaluation solutions are available in the Premium Tier & Rankers Plan.
Unlock Answers (₹1,000)

2(b): Time Estimates and Critical Path in Network Analysis

5 Marks
(i) Network Diagram before Fire Activities 1-2, 1-3 and 1-4 had already been completed before the fire. After fire, 15 days are over and 31 days (46 days-15 days) remain with the following outstanding activities: Activity Duration (Days) 2-4 2-5 3-6 4-6 5-6 Network Diagram after Fire (ii) New Expected Project Duration is 48 days and Revised Critical Path after fire is 2-5-6. (iii) Standard Deviation of the Project = 1.41 Using Z value, we have Z = -1.42 Using area under standard normal curve, the probability of achieving 46 days is = 8%
🔒 Official Model Solution
Model answers and self-evaluation solutions are available in the Premium Tier & Rankers Plan.
Unlock Answers (₹1,000)

3(a): Time Estimates and Critical Path in Network Analysis

5 Marks
Network Diagram: 11 of 13 Various paths of the network are given below: 1 – 2 – 3 – 4 – 6 – 7 with duration = 25 days 1 – 2 – 4 – 6 – 7 with duration = 24 days 1 – 2 – 3 – 5 – 6 – 7 with duration = 23 days 1 – 2 – 5 – 6 – 7 with duration = 24 days (ii) The critical path of the project is A  C  E G or 1 – 2 – 3 – 4 – 6 – 7 with normal duration of 25 days. (iii) Calculation of Cost Slope for various activities: Activity Normal duration Crash duration Normal Cost (₹) Crash Cost (₹) Cost Slope (₹) A (1 – 2) B (2 – 4) -200 C (2 – 3) N.A. D (2 – 5) 1000 E (4 – 6) 1000 F (5 – 6) 1400 G (6 – 7) 1600 Total 4500 Step-1: In order to determine the cost of completing the project in 21 days, let us crash that activity on the critical path which has minimum cost slope. It can be seen that the minimum cost slope of ₹100 corresponds to activity E (4 – 6) and it lies on the critical path. Hence, we crash activity E (4 – 6) by 1 day at an additional cost of ₹ 100. Step-2: Various paths now are 1 – 2 – 3 – 4 – 6 – 7 with duration = 24 days 1 – 2 – 4 – 6 – 7 with duration = 23 days 1 – 2 – 3 – 5 – 6 – 7 with duration = 23 days 1 – 2 – 5 – 6 – 7with duration = 24 days An examination of the above four paths clearly points out that there are two critical paths namely 1 – 2 – 3 – 4 – 6 – 7and 1 – 2 – 5 – 6 – 7, each with duration = 24 days. To reduce the project duration by three days more, there are following possible combination of activities: 1. Crash activities 4 – 6 on the path 1 – 2 – 3 – 4 – 6 – 7 and 5 – 6on the path 1 – 2 – 5 – 6 – 7 by one day each at an additional cost of ₹ 100 + ₹ 200 = ₹300. 2. Crash activities 4 – 6on path1 – 2 – 3 – 4 – 6 – 7and 2 – 5on path1 – 2 – 5 – 6 – 7 by one day each at an additional cost of ₹ 100 + ₹ 100 = ₹ 200. 3. Crash activity 1 – 2 by one day at an additional cost of ₹ 200. It can be observed that the additional cost of reducing the project duration by one day in combination 2 as well as combination 3 is ₹ 200. Hence any of these two can be selected for crashing. However, since crashing activity 1 – 2 by 1 day reduces the duration of all the paths by 1 day, we will crash it by 1 day. The project duration becomes 23 days at an additional cost of ₹ 200. Step-3: Crash activity 1 – 2 by 1 day further, it would reduce the project duration to 22 days at an additional cost = ₹ 200. 12 of 13 Step-4: Activity 1 – 2 cannot be crashed further. So, we now select the combination 2 stated above for crashing. Crash activities 4 – 6 and 2 – 5 by one day each at an additional cost of ₹ 100 + ₹ 100 = ₹ 200. The project duration now becomes equal to 21 days. Hence, in order to complete the project in 21 days, an additional cost of ₹ 100 + ₹ 200+ ₹ 200 + ₹ 200 = ₹ 700 will be incurred. The normal cost of completing the project in 25 days = ₹ 4500. Hence, the percentage increase in cost to complete the project in = 15.55%
🔒 Official Model Solution
Model answers and self-evaluation solutions are available in the Premium Tier & Rankers Plan.
Unlock Answers (₹1,000)

3(b): Time Estimates and Critical Path in Network Analysis

5 Marks
(i) The network diagram for the given data is shown below: SUGGESTED_ANSWERs TO QUESTION_SYL2016_JUNE2018_PAPER-15 Academics Department, The Institute of Cost Accountants of India (Statutory Body under an Act of Parliament) Page 13 Network Diagram (ii) The earliest and latest expected time for each event is calculated by considering the expected time of each activity as shown in the following table: TABLE: CALCULATION OF EXPECTED TIMES AND VARIANCES Activity to tm Tp te = 1 [to + 4tm + tp] σe =[ 1 [tp - to]2 1 – 2 2 – 3 2 - 4 4/9 3 – 5 4/9 4 – 6 4/9 5 – 6 5 – 7 1/9 6 - 7 The expected duration and variance for each activity is shown in the above table. (iii) Critical path is : 1 — 2 — 3 — 5 — 6 — 7. Expected project length. Te = 3+6+6+0+5 = 20 weeks (iv) Probability that the project will be completed in 23 weeks is given by: P(0 ≤ X ≤ 23) = P(0 ≤ Z ≤ 23 - 20 2.444 ) = P(0 ≤ Z ≤ 1.920) = 0.9726 or 97.26%. (b) A B C D E Selling Price Variable Cost Contribution Let a, b, c, d, e be the number of units respectively of A,B,C,D and E to be produced. Objective function: Maximise contribution: Z = 30a+24b+32c+40d+14e Subject to: Demand Constraint a ≤ 3000 b ≤ 2400 c ≤ 1800 d ≤ 1200 e ≤ 1200 Special Raw Material availability constraint 2a + b + 4c + 3d + 6e ≤ 11600 Special raw material cost constraint 12a + 6b + 24c + 18d + 36e ≤ 60,000 SUGGESTED_ANSWERs TO QUESTION_SYL2016_JUNE2018_PAPER-15 Academics Department, The Institute of Cost Accountants of India (Statutory Body under an Act of Parliament) Page 14 Non negativity constraint: a,b,c,d,e ≥ 0 8. Write short notes on any four of the following: 4x4= 16 (a) Backflush Accounting (b) Relevant Cost Analysis (c) Treatment of Variances in cost accounts (d) Value Engineering (e) Life Cycle Costing Answer:
🔒 Official Model Solution
Model answers and self-evaluation solutions are available in the Premium Tier & Rankers Plan.
Unlock Answers (₹1,000)
Advertisement

Quick Pomodoro Timer

Select a focus duration to launch your session:

25m Standard 50m Deep Focus 15m Quick Sprint
🎧 Join Virtual Focus Room (with 40Hz Audio) →
🔔
Daily Study Reminders
Get notified 15m before your target study sessions.